Safety inspection prompts crane upgrade at Bayswater Power Station

Rockwell Automation Australia
Thursday, 03 October, 2013


To comply with safety requirements, Macquarie Generation’s Bayswater Power Station underwent a routine inspection of its aging cranes. As a result, the company called on the domain expertise of Rockwell Automation to deliver a solution for the cranes to meet current safety standards.

The Bayswater Power Station, in the Upper Hunter Valley area of NSW, is one of two stations owned and operated by Macquarie Generation. Each year the company produces approximately 13% of the electricity required by people in eastern Australia, making Macquarie Generation one of the country’s largest electricity generators.

Bayswater's design reflects the progress and improvements in power-generation technology to maximise efficiency and minimise environmental impacts. The most distinctive feature of Bayswater Power Station is the four evaporative cooling towers.

Over recent years, Bayswater Power Station has produced approximately 15,000 GWh of electricity a year. This is enough power for two million average Australian homes.

Following a mandatory 25-year inspection, Macquarie Generation recognised that two of the station’s overhead cranes required upgrades to their drive systems to meet current Australian safety standards and to address obsolescence issues.

Bayswater Power Station’s T1 Crane used during power station outages to service power generators.

Bayswater Power Station’s T1 Crane used during power station outages to service power generators.

With a commitment to the improvement of operation and technology upgrades, Macquarie Generation called on the expertise of the Rockwell Automation Solutions team to project manage, design, manufacture, install and commission a solution to meet the company’s requirements.

The primary role of the cranes is for use during generator shutdowns, which take place once or twice a year depending on what is required when work is suspended.

According to Peter Tomazic, Solutions Consultant for Rockwell Automation, “The primary role of the cranes is to lift equipment in and out, as required, during outages. When the power station is running normally these cranes generally sit idle.”

Designing a cost-effective solution to customise the electrical system to fit through the manholes of the existing crane structures presented some unique challenges that would call on the risk management expertise of Rockwell Automation.

During the risk assessment it was found that the cranes’ access manholes were not large enough to allow installation of standard gear plates or new control cabinets.

“We discovered, post audit, that we would be putting the new solution into a very crammed electric house,” said Tomazic.

The crane drive systems are usually pre-installed in cabinets and the existing electrics had all been mounted into the frame of the crane, so that access into it was much like a ship hole door. It appeared as if, when the cranes were originally built, there was a bigger opening and the manufacturer had then built around it.

“As a result of this, we had to cross off an earlier idea to design entirely new cabinets, which would have made the job much easier,” said Tomazic.

“Instead, we decided to manufacture the insides of the electric drive cabinet in a manner that could be brought into the existing crane electrics and fitted into the existing cabinets once they were gutted.”

Rockwell Automation provided a custom-designed and manufactured solution consisting of GuardLogix and PowerFlex DC drives mounted on custom-built gear plates for installation in the original crane cabinets.

The challenges presented in this project required something that was not simply an ‘off-the-shelf’ solution. According to Tomazic, “We are often awarded contracts that require our engineers to ‘scratch their heads’ a little bit to come up with the best solution. Our local engineering team manages many upgrade projects to help reduce the customer’s risk, supplying projects on time and within budget.”

Once the obstacle of a ‘crammed’ electrics house was overcome by Rockwell Automation, Macquarie Generation was able to realise the outcomes it was expecting.

The GuardLogix controllers allowed safety to be integrated into the system, and addressed what was required by current Australian safety standards for these applications. The solution also incorporated an innovative data-logging capability within the GuardLogix system using the Historian ME module.

“The cranes’ operating data was previously difficult to record with the obsolete analog system, so to fix that we provided a solution that was capable of logging the operating data of the cranes, which the company required for tracking crane usage,” said Tomazic.

The key outcome from this project is that it has reinvigorated Bayswater Power Station’s two cranes to safely and reliably take the station through many more outages.

Along with both cranes now adhering to current Australian safety standards, the design offers a fault-tolerant system that does not compromise the safety of the crane in the event of a single failure.

According to Satish Busuapala, Acting Team Leader at Bayswater Power Station, “The project, awarded to Rockwell Automation in October 2011, took about a year to complete and Macquarie Generation is very pleased with the outcome.”

“The cranes, they have been performing well since the upgrade,” he continued.

Rockwell Automation attended to the whole life cycle of the project from the safety-risk assessment, to the design, manufacture and commissioning of the project.

“We needed to have the cranes certified for them to be at current standards and Rockwell Automation achieved that for the power station. Macquarie Generation would have no hesitation in working with Rockwell Automation again as further upgrades are required,” concluded Busuapala.

Related Articles

Water authorities improve efficiencies with standardised RTUs

Kingfisher modular remote telemetry units (RTUs) have been installed at water and wastewater...

Converting oilfield gas flares into revenue

Mexican oil company Nuvoil built a gas conditioning plant in just nine months and captured...

IIoT solution enables water company to leverage data insights

A major Chinese wastewater treatment plant uses Siemens Insights Hub to digitalise operations.


  • All content Copyright © 2024 Westwick-Farrow Pty Ltd